1. Process control is carried out
- before production
- during production
- after production control
- All of the above
2. Low cost, higher volume items requires
- no inspection
- little inspection
- intensive inspection
- 100% inspection
3. High cost, low volume items requires
- no inspection
- little inspection
- intensive inspection
- 100% inspection
4. The mean of sampling distribution is
- less than mean of process distribution
- more than mean of process distribution
- equal to mean of process distribution
- any of the above
5. The percent of the sample means will have values that are within ±3 standard deviations of the distribution mean is
- 95.5
- 96.7
- 97.6
- 99.7
6. The dividing lines between random and non random deviations from mean of the distribution are known as
- upper control limit
- lower control limit
- control limits
- two sigma limits
7. The chart used to monitor variable is
- Range chart
- p-chart
- c-chart
- All of the above
8. The chart used to monitor attributes is
- Range chart
- Mean chart
- p-chart
- All of the above
9. Central tendency of a process is monitored in
- Range chart
- Mean chart
- p-chart
- c-chart
10. Dispersion of a process in monitored in
- Range chart
- Mean chart
- p-chart
- c-chart